1 病房区/Patient bays
科罗拉多会议中心临时护理中心位于科罗拉多州丹佛市,被打造成一座拥有2000 张床位的医疗机构,以应对新冠病毒疫情对该市造成的病床需求激增。展览大厅层可容纳病情稳定的新冠阳性患者,为其在出院前提供氧气。该项目需要一种实际的设计构建交付方法,采用模块化设计,使用了毗邻中央护士站约3m×3m(10ft×10ft)的病患隔间。贮藏及辅助空间位于每排病房的尽头。每个展厅均设有患者淋浴室。一间小药房坐落在中心地带,由位于会议中心低层的主药房供给。现有的中庭空间被重新用作员工休息室,而F 展厅则被用于放置员工储物柜和员工淋浴设施。消防部门要求设计团队使用防火建筑材料,使得该中心不同于全国的其他设施。最后,团队共使用了25,330 块石膏板墙、35,695 根金属龙骨、长约9.7km(6 英里)、14 吨重的输氧管道、逾32km(20 英里)的应急电源管道、可前往每间病房的护士呼叫站以及其他众多材料,全部在18 天内交付。(王单单 译)
2 患者淋浴室/Patient shower rooms
3 整体平面/Overall floor plan
The Colorado Convention Centre Alternate Care Facility in Denver, Colorado was designed and built as a 2000-bed facility to respond to the rapid demands that the COVID-19 pandemic placed on the City. The Exhibit Hall level houses and supports COVID positive patients who are in stable condition needing oxygen prior to fully discharging them to their homes. The pace of this project required a handson design build delivery method. The design was modular using 10×10 ft patient bays located adjacent to central nurse stations. Supplies and support spaces were at the ends of each patient row, and patient showers were installed in each Exhibit Hall. A small centrally located pharmacy was fed by a main pharmacy on the lower level of the Convention Centre. Existing atrium spaces were re-purposed for Staff Lounges, and Exhibit Hall F was used for staff lockers and staff shower facilities. This facility is different from others built around the country as the fire department required the team to use fire-resistant building materials. In the end, the team used 25,330 sheets of drywall, 35,695 metal studs, 6 miles (14 tons) of piped oxygen, over 20 miles of conduit for emergency power, a nurse call station to every patient room and many more materials. All were delivered in 18 days.
4 患者洗手站/Patient hands wash station
5.6 施工过程/Construction process
7 病房内景/Patient room interior
8 病房区/Patient bays
项目信息/Credits and Data
地点/Location: 美国科罗拉多州丹佛市/Denver, Colorado, USA
客户/Client: 科罗拉多州/State of Colorado
主持建筑师/Principal Architects: Ann H. Adams (On-site Design Principal), Scott Nevin (Principal in Charge), Peter Carlson (Support Principal)
设计团队/Design Team: Guadalupe Cantu, Lauren Cooper, Tina Du Mond, Emily Johns, Jeff Leland, Collin McDougall, Abby Noble
合作/Collaborators: United States Army Corp of Engineers, ECC, Hensel Phelps, Davis Partnership Architects, Fentress Architects, RMH Group, Maxon Engineering
暖通、电气及给排水工程/MEP Engineers: RMH Group
总承包/Contractor: Hensel Phelps
材料/Materials: 石膏板墙,钢龙骨/Drywall, Steel Studs
建筑面积/Floor Area: 约53,605 m2/577,000 ft2
设计周期/Design Period: 18天/18 days
建造时间/Construction Period: 2020.04
竣工时间/Completion Time: 18天/18 days
绘图/Drawings: ©Davis Partnership Architects